Power
NERC introduces N25,000 levy on generators
LAGOS – The Federal Government is set to reap billions of naira from the importation of generating sets, as the Nigeria Electricity Regulatory Commission, NERC, has introduced a N25,000 charge per unit of 100KVA generator imported into the country.
The NERC, in its recently released, ‘Guidelines for obtaining Clearance Certificate for the importation of generating sets and related matters,’ also fixed a charge of N3,500 per unit of between 25kva and 100kva generators imported into the country, while generators between 5kva and 25kva attract a charge of N1,000 per unit.
Other charges are: N250 per unit of between 2.5kva and 5kva, while between 0.45 Kva and 2.5 Kva generators attract a charge of N150 per unit.
The NERC is also charging 10 per cent of the fee paid on the initial certificate for renewal of import licenses.
The significance of this policy becomes enormous, especially when viewed against the backdrop that a couple of years ago, Nigerian businesses spent about N1.8 billion on importation of generators within one week.
This was contained in a data obtained from the Central Bank of Nigeria, CBN, which shows that 15 firms purchased $8.2 million from the CBN in one week to import generators alone.
Also, couple of weeks ago, another report published by a global research firm, GBI Research, projected that the importation of generating sets in Nigeria is expected to grow to about N151.16 billion ($950.7 million) by the year 2020.
According to the research firm, Nigeria, which is the largest market for diesel and gas generating sets in Africa, is forecast to see growth rate of about 8.7 per cent to drive up market volume from N71.55 billion ($450 million) in 2011, to about N151.16 billion ($950.7 million) by 2020.
The research firm expects the growth in the Nigerian generating sets market to be driven by the epileptic power situation in the country going by the current state of generation, transmission and distribution networks, and economic growth in the country.
Importation guidelines
The NERC, in the document obtained on its website, signed by the Chairman/Chief Executive Officer, NERC, Dr. Sam Amadi, said the provisions of the guidelines cover every importation into Nigeria. This includes fully assembled generators and knocked-down parts imported for domestic assembling of electric generating sets or retail as spares.
To qualify for the license to import generators into the country, the NERC said every applicant shall submit annual report of generating sets or knocked down parts imported by them in the last 12 months. The report is expected to show the various capacities and the number sold in each category.
The NERC further stated that the annual report of generating sets imported should be submitted before the end of the first quarter of the following year.
The NERC is also seeking to regulate the noise level of generators in the country, as those with noise level above the stated minimum will not be allowed into the country.
It said: “A certificate may be issued for the importation of generating sets or knocked down parts which comply with the relevant provisions on noise level of 35 decibels, as specified under the National Environmental (Noise Standards and Control) Regulations 2009, issued by the National Environmental Standards and Regulations Enforcement Agency (NESREA), and as amended from time to time.
“Every imported and locally assembled generator shall be fitted with optimizers to reduce environmental pollution arising from incomplete combustion.”
Continuing, the NERC said: “A certificate issued by the Commission under these Guidelines shall be for a period of six months only from the date of issue, provided that where a certificate is not utilized for the importation of generating sets or knocked down parts of generating sets stated therein, such certificate shall lapse.
“A certificate may be renewed for a further period of six months and no more subject to the payment of renewal fees.
A certificate issued by the Commission shall be for the purpose of importation of the generating sets and or knocked down parts listed therein and none other whatsoever.
“An application for renewal of clearance certificate shall be within 30 days after the expiration of the initial clearance Certificate issued.
– VANGUARD
Power
Nigeria To Face Increase In Electricity Tariffs From July
According to reports, Nigeria’s population may face more challenging times ahead as electricity tariffs are projected to increase by over 40 percent in the near future.
This rise in tariffs could ultimately result in the elimination of all energy subsidies in the country.
Currently, the electricity sector relies on a monthly subsidy of approximately N50 billion, stemming from a shortfall in revenue.
The tariff hike, scheduled to take effect from July 1, will pose another significant test for President Bola Ahmed Tinubu’s administration and its ongoing market reforms.
The government has already taken steps to remove subsidies on Premium Motor Spirit (PMS) and implemented a floating exchange rate for the national currency.
These decisions have added complexity to the price-setting process of the Nigerian Electricity Regulatory Commission (NERC) and its 2022 Multi-Year Tariff Order (MYTO).
Despite power sector players failing to meet the target of supplying a minimum of 5,000 megawatts, even after signing contracts with the Nigerian Electricity Regulatory Commission (NERC), the current Service Based Tariff (SBT) is based on an exchange rate of N441/$ and an inflation rate of 16.97 percent.
According to NERC’s directives in 2015, the average tariff for distribution companies (DisCos) and different categories of end-users was N25 per kilowatt, as per Order 198/2020, which came into effect on September 1, 2020.
However, in the MYTO for 2022, the average tariff increased to N60 per kilowatt across all customer categories, and in the most recent update, it stands at N64 per kilowatt.
The determination of the 2015 tariff relied on a foreign exchange rate of N198.97/$, which increased to N383.80/$ in 2020 and further to N441.78/$ in 2022. In terms of inflation, the 2015 MYTO utilized an 8.3 percent rate, which rose to 12 percent in 2020 and reached 16.97 percent in 2022.
Currently, the inflation rate stands at 22.41 percent, and experts predict it could reach 30 percent by the end of June, considering the floating of the naira and the removal of subsidies on Premium Motor Spirit (PMS).
The tariff determination process takes into account various factors, including the significant metering gap of over seven million, gas prices, losses within the system, and the actual generation capacity. These elements play a role in determining the final tariff.
As anticipated, NERC had projected that the tariff for July 2023 would eliminate subsidies and introduce increases to the previously frozen tariff bands D and E.
These adjustments were intended to raise the bands from N54.59/kilowatt to N62.16 for band D and from N48.37/kilowatt to N61.16 on average. Moreover, the average increase across all bands was expected to reach N67/kilowatt.
However, due to the ongoing floating of the naira and the significant inflationary pressures, it is now projected that the new average tariff will need to be approximately N88/kilowatt for the power sector to recover its costs.
According to energy lawyer Madaki Ameh, the continuous and frequent increases in power tariffs are akin to a form of blackmail against electricity consumers.
Amen said “Indexing the cost of electricity on the dollar is a huge mistake because most of the inputs for electricity supply are local. The DisCos are also holding Nigerians to ransom by failing to increase the supply base, thereby spreading the tariffs across a broader spectrum of consumers to reduce the unit cost of electricity.”
He insisted that as long as there remain many unmetered consumers and many others not connected to the grid at all, the few consumers on the grid would continue to be subjected to unjust tariffs, which are not reflective of the quality of service delivered.
Ameh hoped that the signing into law of the new Electricity Act would mark “the beginning of light at the end of the long tunnel of inefficient and epileptic power supply in Nigeria.”
Segun Ajibola, the former President of the Chartered Institute of Bankers of Nigeria (CIBN) and a professor of Economics at Babcock University, highlighted that there remains a gap between the cost of electricity and the value it provides in exchange.
“Nigerians are still struggling to keep pace with the cost of energy for business and household use. If the electricity tariff goes up as envisaged, the question remains if there will be value for the quantum of electricity so paid for.
“The truth remains that if electricity supply is constant, of the right quantity and quality, the envisaged upward review in the tariff will be gladly absorbed by the populace,” he said.
Lanre Elatuyi, an Electricity Market Analyst, expressed that the recently implemented tariff rate would have significant implications. He emphasized that the devaluation of the Nigerian currency poses a major challenge for companies with dollar-denominated loans to repay.
He said “They will need more naira today to buy a dollar. They need to manage their exposure to foreign exchange risk. Even operators of hydro plants pay their concession fees in dollars. So, wholesale electricity price will be adjusted upward and this will get to the end users’ tariffs too.”
Power
Buhari’s Gov, State Governors Secretly Sold 5 Power Plants – Shehu Sani
Senator Shehu Sani, a prominent Nigerian lawmaker has accused President Muhammadu Buhari’s government and state governors of secretly selling five power generating plants without disclosing the utilization of the funds received.
He disclosed this in his Twitter handle on Monday.
Senator Sani, known for his outspoken nature and activism expresses his concerns over the alleged undisclosed sale of the power plants.
He claimed that the government, in collaboration with state governors, had carried out the transactions without informing the Nigerian public about the purpose of the funds acquired from the sale.
The post reads “Buhari’s Government in collaboration with the State Governors quietly sold the five power generating plants without telling the country what the money was used for.
Power
Nigeria’s VP Inaugurates 240MW Afam 3 Fast Power Project
The Vice President of Nigeria, Prof. Yemi Osinbajo, has inaugurated the Afam 3 Fast Power 240-megawatt turbine project in Rivers State.
The project, which is a subsidiary of the Transcorp Group located in Oyigbo, on the outskirts of Port Harcourt in the state, was unveiled during a ceremony that took place on Tuesday.
The event, which was attended by several dignitaries, including the Chairman of Transcorp Group, Tony Elumelu, and other top officials, saw the Vice President arriving at the venue in a chopper at exactly 11:35 am.
Upon his arrival, he was escorted into the premises where he officially inaugurated the project.
During his speech at the event, he disclosed that the acquisition of the project was approved by the National Council on Privatisation (NCP) and the acquisition cost was ₦105.3 trillion.
Osinbajo further emphasized that the successful completion of the project is a significant breakthrough in Nigeria’s power sector.
In his address, Osinbajo said, “In 2020, electricity subsidies reached N584 billion, but service-based tariffs have led to a doubling of collection in the Nigeria Electricity Supply Industry from N40 billion in 2020 to N80 billion in the first quarter of 2023.
“If this trajectory continues, the Nigeria Electricity Supply Industry will be able to pay for itself. Our administration has also created programs for off-grid for electrification. Rural Electrification Agency now has the capacity to provide electricity supply on a first-class basis.
“We are on track to electrify all Nigerians in the next decade. However, we will not make progress if our gas supply does not improve. The gas supply challenges are hampering improvements.”
He further lauded General Electric, the National Council on Privatization (NCP), and the host communities for their contribution to the completion of the Afam 3 Fast Power 240-megawatt turbine project in Rivers State.
Osinbajo highlighted that the successful completion of the project will significantly increase the country’s power supply capacity, leading to a better quality of life for Nigerians.
In November 2020, the federal government and the Transcorp Power Consortium signed a share sale and purchase agreement in relation to Afam Power Plc and Afam 3 Fast Power Limited.
The National Council on Privatization approved the privatization of the Afam Power Plant back in August 2017, which triggered a competitive bidding process involving 12 prospective investors.
After careful consideration, Transcorp Power Consortium emerged as the preferred bidder with a combined offer of N105 billion.