Connect with us

Energy

Experts point to Solar, Coal, Hydro power, as gas challenges persist

Published

on

ABUJA – Gas supply shortages affecting power supply in many parts of the country have reinforced the need for the government to speed up efforts at diversifying the nation’s power generation mix, which is currently largely dependent on gas, analysts have said.

Nigeria’s electricity generation has continued to fluctuate between 2,500 megawatts (MW) and 4,600 MW in recent years, with the failure of the federal government to achieve its planned 10,000 MW by December 2013.

Meanwhile, the country, with a population of about 170 million people, is estimated to need about 40,000 MW of electricity over the next decade, but current generation capacity falls far short of the almost 13,000 MW required to meet current peak demand.

Experts say diversification of the generation mix would help to lift power supply in the nation.

Experts point to Solar, Coal, Hydro power, as gas challenges persistThey add that to minimise the current supply challenges being faced with gas supply, other fuel sources such as solar, coal and hydro-power should be fully explored in order to ensure diversified electricity sources that will promote electricity availability and reliability.

The need for more incentives to boost the commercialisation of renewable energy technology in the country as alternative source of electricity supply was identified as critical to facilitating further investments.

“There is no doubt Nigeria needs to diversify its energy resource inputs for power. Gas is better as a peak demand source. Coal serves well as a base-load source. I am an advocate of energy resource mix in the power sector. The use of oil to power generators is ludicrous and a waste of a scarce resource.

“ Nigeria must wake up to that. But if we have to rely on gas as a transition fuel, we must explore more aggressively, but we are not. Neither are we doing much for coal as we should,” said Wumi Iledare, president of the International Association for Energy Economics and director, Emerald Energy Institute, University of Port Harcourt.

Atedo Peterside, chairman of the Technical Committee, National Council on Privatisation, speaking at a conference weeks back, had said that while gas supply constraints arising from capacity shortfalls/lags could be foreseen, the impact of pipeline vandalisation was not so predictable and could induce damaging shocks to the health of the entire electricity value chain.

“It has become increasingly likely that renewable energies will provide more of the world’s electricity than gas-fired power plants by 2016, as its declining cost profile positions it to compete more vigorously with fossil fuels”, says a new report by Ecobank Oil, Gas and Energy Research headed by Rolake Akinkugbe.

According to the report titled ‘Fully charged: Key dynamics in Middle Africa’s Power Sector in 2014’, Ghana is leading the rest of West Africa in driving the renewable energy agenda with its 2011 Renewable Energy Act. The country plans to invest at least $1 billion in renewable energy projects in next 7 years to 2020.

“Costs tend to be high for renewable energy projects in Africa due to equipment imports, higher internal transport costs, import levies. Developing local manufacturing capabilities and increasing the share of local content for renewable power generation projects can help reduce costs, which are predicted to decline over time,” the report said.

Adeola Adenikinju, president of Nigerian Association for Energy Economics and director, Centre for Petroleum, Energy Economics and Law, University of Ibadan, said in the short term, the focus would remain on gas due to a number of economic factors and the relatively shorter term of completing a gas-fired thermal plant.

“However, in the medium term and to avoid or minimise the current challenges we are facing with gas supply, we must be thinking of dual-fuel plants, and other fuel sources both renewable and non-renewable, in order to ensure energy security, a diversified electricity source that will promote electricity availability, reliability and enhance electricity access,” he said.

Adenikinju added that there are currently very limited incentives to boost commercialisation of renewable energy technology as alternative source to electricity supply, citing Germany and China as examples worth studying for Nigeria.

The Ecobank report released on January 30, 2014 stated that the full penetration of renewable energy into the African market would largely hinge on investment security underpinned by regulation.

“Many countries in sub-Saharan Africa have renewable potential that is many times their current demand for electricity, but most private sector executives view national targets and Feed-in-Tariffs as the most powerful incentive mechanisms required to accelerate renewable energy development in the region,” the report said.

Oladiran Ajayi, energy expert and a senior associate with Templars law firm, said considering the relative costs of alternative sources of energy, the nation should pursue them, but not at the expense of gas development.

Last year in August, the federal government signed a $3.7bn memorandum of understanding with a Nigerian-Chinese consortium, HTG-Pacific Energy, for the development of a 1000- to 1200-MW coal-fired power plant in Enugu state. The plant is expected to be operational in the next four years.

Also, in late January the government said it was building over 200 new dams in order to achieve its target of 10,000MW of electricity at the end of this year, according to Vice President Namadi Sambo.

Nigeria, with a population of about 170 million people, is estimated to need about 40,000 MW of electricity over the next decade, but current generation capacity falls far short of the almost 13,000 MW required to meet peak demand.

– BUSINESS DAY

Click to comment
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments

Energy

NNPC Ltd Declares 100% Pipeline Availability for First Time in 2 Decades

Published

on

For the first time in 20 years, Nigeria has recorded 100 percent availability of its major pipelines.

According to the Nigerian National Petroleum Company Limited (NNPC Ltd) the development is predicated on the implementation of an integrated pipeline security framework involving security agencies, pipeline operators and host communities.

The Group Chief Executive Officer of NNPC Ltd, Bayo Ojulari, disclosed this at the 2026 Nigeria International Pipelines Technology and Security Conference (NIPITECS 2026) in Abuja.

READ ALSO: Shell Commends Oil Industry Reforms as Key to Unlocking More Barrels

The two-day event was organised by the Pipelines Professionals Association of Nigeria (PLAN) under the theme: “Financing the Future: Unlocking Capital for Resilient Pipeline Infrastructure in Nigeria.”

Ojulari, who was represented by the Head of NNPC Gas, Audu Ibrahim, said pipeline availability had remained between 95 and 100 percent over the preceding 18 months, attributing the improvement to the security framework coordinated by the Office of the National Security Adviser, alongside enhanced surveillance and community engagement.

He said the improved security situation had contributed to increased crude oil production, which rose to 1.71 million barrels per day, the highest level recorded in five years.

The NNPC Ltd boss also disclosed that recovery across Nigeria’s five crude oil terminals averaged 98 percent between April 2025 and May 2026, reflecting improved operational efficiency across the country’s oil infrastructure.

According to him, the progress recorded in pipeline security and availability underscores the importance of sustained collaboration among government agencies, industry operators and host communities in protecting critical national energy assets.

On gas infrastructure development, Ojulari said Nigeria’s gas production had reached 7.5 billion standard cubic feet per day, with the government targeting 10 billion standard cubic feet daily by 2027 and 12 billion by 2030.

He said the targets were backed by Nigeria’s estimated 215 trillion cubic feet of gas reserves, the Petroleum Industry Act (PIA), the Decade of Gas Framework and the Gas Master Plan.

Ojulari further disclosed that the NNPC Ltd had signed gas sales and purchase agreements covering 1.29 billion standard cubic feet per day for long-term supply and 750 million standard cubic feet per day for domestic industrial use.

He said the agreements represented more than $20 billion in associated investments, adding that reliable pipeline infrastructure remained critical to translating the country’s gas resources into electricity, industrial development and economic growth.

On major gas transportation projects, he said the 640-kilometre Ajaokuta-Kaduna-Kano (AKK) gas pipeline had reached about 95 per cent completion, with gas delivery to Abuja expected before the end of 2026, followed by Kaduna and Kano.

The 40-inch pipeline, valued at approximately $2.8 billion, is designed to transport up to 2.2 billion standard cubic feet of gas daily to support power generation, fertiliser production and manufacturing.

He also highlighted progress on the 130-kilometre Obiafu-Obrikom-Oben (OB3) gas pipeline, designed to transport up to two billion standard cubic feet of gas daily.

According to him, the NNPC Ltd completed the technically challenging Niger River crossing on April 3, 2026, using horizontal directional drilling technology, while pre-commissioning was completed in August.

Ojulari said the project would strengthen connectivity across Nigeria’s eastern and western gas networks and improve the country’s overall gas transportation capacity.

He stressed that sustained investment in pipeline infrastructure, technology and security would be essential to achieving Nigeria’s energy ambitions.

Meanwhile, the President of PLAN, Engineer Ngozi Adeleke, called for increased investment, stronger collaboration and the deployment of advanced technology to strengthen the country’s pipeline infrastructure.

Adeleke said pipelines remained the backbone of the energy value chain, connecting producing fields to processing facilities, power plants, industrial centres, export terminals and consumers.

She said the association would continue to promote professionalism, operational excellence, safety, integrity and capacity development across the pipeline industry.

According to her, PLAN would also sustain its advocacy for policies and practices that encourage local and international investment in critical pipeline infrastructure.

She urged operators, financiers, regulators, technology companies, service providers, academia and host communities to work together to develop practical solutions to the sector’s financing, security and operational challenges.

Adeleke said the association would use the conference as a platform to foster partnerships, stimulate innovation and encourage knowledge sharing capable of advancing Nigeria’s pipeline ecosystem.

Continue Reading

Energy

NMDPRA Gets Senate Nod for Six Executive Directors

Published

on

Senate asks NLNG to pay host communities N18.4b compensation within 2 months 

The Senate has confirmed the appointments of six Executive Directors of the Nigerian Midstream and Downstream Petroleum Regulatory Authority (NMDPRA).

The confirmation followed the consideration and adoption of a report by the Senate Committees on Petroleum Resources (Downstream) and Petroleum Resources (Gas), presented by Senator Suleiman Kawu (Kano South), on Tuesday.

Those confirmed for reappointment are Abiodun Adeniji, Executive Director, Finance and Accounts; Ogbugo Ukoha, Executive Director, Distribution Systems, Storage and Retailing Infrastructure; and Dr Mustapha Lamorde, Executive Director, Health, Safety, Environment and Community.

READ ALSO: Atiku Accuses Tinubu of Seeking Plateau’s Forgiveness Only for 2027 Votes

The three nominees approved for new appointments are Mobolaji Musa, Executive Director, Hydrocarbon Processing Plants, Installation and Partnership; Ogechukwu Modie, Executive Director, Economic Regulation and Strategic Planning; and Said Abutalib, Executive Director, Corporate Services and Administration.

The confirmation followed a request by President Bola Tinubu to the Senate to screen and confirm the appointments of the executive directors and the Secretary of the NMDPRA Board.

Tinubu’s request was conveyed in a letter addressed to Senate President Godswill Akpabio and read during plenary last week.

Continue Reading

Energy

Financiers Stake $1.5bn on AKK Gas Pipeline on Projected Throughput

Published

on

The sum of $1.5 billion was raised to finance the Ajaokuta-Kaduna-Kano (AKK) Gas Pipeline Project, on the basis of the projected throughput from the facility.

The Nigerian National Petroleum Company Limited (NNPC Ltd) made the disclosure, as the state oil major moves towards completing the 614-kilometre infrastructure designed to expand gas supply across northern Nigeria.

Group Chief Executive Officer of the NNPC Ltd, Bashir Ojulari, stated this in an interview with the News Agency of Nigeria (NAN) in Abuja at the weekend, explaining that the financing was secured solely on the basis of anticipated gas transportation volumes through the pipeline.

According to Ojulari, the mainline section of the project had been completed, with overall execution reaching 95 percent, while the outstanding 5 percent involved completing some stations and connecting the pipeline to end-users.

READ ALSO: Axxela Expands Ogun Gas Network with New 17km Pipeline

He said the company was targeting the delivery of gas to Abuja before the end of 2026, with Kaduna and Kano expected to receive supplies in 2027.

“The AKK gas pipeline, all the way from Ajaokuta, Kaduna to Kano, the main pipeline has been completed. The remaining 5 percent has to do with some of the stations where we need to then link offtakes from the main pipeline to users.

“We are hoping that before the end of the year, we will get the gas to Abuja, which is the first step, and by 2027 we will get the gas to Kaduna and Kano,” Ojulari said.

The $1.5 billion financing is significant as it demonstrates the potential of the country’s gas transportation infrastructure to attract funding based on projected commercial flows, rather than relying exclusively on conventional government-backed financing.

Ojulari said the pipeline would support power generation, factories, data centres and industrial hubs, while also improving the availability of Compressed Natural Gas (CNG) across the northern region.

He explained that the completion of the mainline would make it easier to extend gas supply to additional locations, reducing the difficulty and cost associated with transporting gas from southern Nigeria to the North.

“We already solved the first line because we now have the Abuja power plant. As we move north and we build those connections, the CNG availability will increase phenomenally.

“But keep in mind that we still then have to go towards Maiduguri and Sokoto, right? So there’ll be more work to be done, but it’s now much easier than just taking gas from all the way from Port Harcourt to those locations,” he added.

The NNPC Ltd chief explained that although the main pipeline had been completed, additional infrastructure would be required to extend distribution to other northern locations, particularly Maiduguri and Sokoto.

The AKK project is a 40-inch, 614-kilometre pipeline system running from Ajaokuta in Kogi State to Kano, with associated intermediate and terminal gas facilities and other equipment designed to transport natural gas to industrial and other off-takers.

Its completion is expected to expand access to domestic gas, support electricity generation and provide feedstock for industries, while opening up opportunities for greater CNG penetration in northern Nigeria.

Continue Reading

Copyright © 2022. Biztellers, powered by Alphaxristi.

0
Would love your thoughts, please comment.x
()
x