Nigeria approves Siemens 25,000 Mw power expansion contract

Published

on

Nigeria approves Siemens 25,000 Mw power expansion contract

Modupe ASUDO

LAGOS-THE Federal Government of Nigeria has approved Siemens’ pre-engineering contract to commence work on the significant expansion of Nigeria’s electricity transmission and distribution network and also generation capacity. The pre-engineering contract forms the initial step in the Presidential Power Initiative (PPI), formerly the Nigeria Electrification Roadmap, outlined by Siemens and the Federal Government of Nigeria in July 2019.

The PPI project aims to upgrade the electricity network to achieve operational capacity of 25,000 megawatts (MW) from the current average of around 4,500 MW, through a series of projects spanning three phases.

Siemens will begin pre-engineering works for the transmission, distribution and meter data management systems (MDMS) infrastructure across the country, to enable the development of a functional, efficient and reliable electricity grid system. Comprehensive studies and power system analysis software for the Nigerian utilities are also included.

Nigeria’s power system is suffering from an imbalance between power generation and demand. Despite more than 8,000 MW of operational power generation capacity in the country, only an average of 4,500 MW reliably reaches consumers.

This inadequate power supply results in regular brownouts and blackouts and has restrained Nigeria’s economic development. Raising Nigeria’s operational electricity capacity to 25,000 MW will power various industries and businesses, as well as significantly improve access and reliability of power supply to the Nigerian people.

This project will also facilitate the creation of thousands of jobs, while generating new opportunities for small and medium enterprises (SMEs) across the country. This will in turn increase Nigeria’s GDP and boost economic productivity.

“This significant, timely and high-level intervention between President Buhari and Chancellor Merkel addresses critical infrastructure deficits in the value chain and helps reposition the power sector to become more attractive, viable and investable,” said Saleh Mamman, Minister of Power, Federal Republic of Nigeria.

“The Government loses over $1 billion annually due to technical and commercial inefficiencies along the electrification value chain. The PPI will help eliminate these inefficiencies and unlock economic value for the country,” said Zainab Shamsuna Ahmed, Minister of Finance, Federal Republic of Nigeria.

“The PPI aligns very strongly with the key objectives of the power sector reforms initiated by Government and superintended by the Bureau of Public Enterprises, which were to attract private sector investment into the power sector, increase operational efficiencies and improve service delivery to end users,” said Alex A. Okoh, Director General, Bureau of Public Enterprises, Federal Republic of Nigeria.

“This contract is one important step as part of the development of vital electrification infrastructure that will ensure reliable power supply, remove constraints in Nigeria’s electricity grid, secure additional revenue for investors, and build competent local content and capacity,” said Onyeche Tifase, Managing Director Siemens Nigeria. “The projects will create vital direct and indirect jobs for Nigerians and local businesses, thus enabling economic growth and increased productivity, based on the supply of reliable electricity.”

The pre-engineering contract is the start of a longer-term approach. Phase 1 of the PPI will focus on essential and quick-win measures to increase the system`s operational capacity to 7,000 MW and to significantly reduce the ATC&C financial losses. As part of Phase 1 Siemens will provide general technical training on core competency areas as well as training for employees of Nigeria’s 11 electricity distribution companies, the Transmission Company of Nigeria, and regulators, on all the equipment and software being provided by Siemens.

Phase 2 will target the remaining network bottlenecks to enable full use of existing generation and distribution capacities, bringing the systems operational capacity to 11,000 MW.

Phase 3 will develop the system up to 25,000 MW in the long-term. This includes upgrades and expansions in both generation, transmission and distribution.

Siemens has been active in Nigeria since the 1950s, and in addition to major power plants, has also supplied and installed more than 100 small gas turbines and compressors in onshore and offshore oil and gas facilities.

This press release and a press picture are available at www.siemens.com/press

Siemens AG (Berlin and Munich) is a global technology powerhouse that has stood for engineering excellence, innovation, quality, reliability and internationality for more than 170 years. The company is active around the globe, focusing on the areas of power generation and distribution, intelligent infrastructure for buildings and distributed energy systems, and automation and digitalization in the process and manufacturing industries. Through the separately managed company Siemens Mobility, a leading supplier of smart mobility solutions for rail and road transport, Siemens is shaping the world market for passenger and freight services. Due to its majority stakes in the publicly listed companies Siemens Healthineers AG and Siemens Gamesa Renewable Energy, Siemens is also a world-leading supplier of medical technology and digital healthcare services as well as environmentally friendly solutions for onshore and offshore wind power generation. In fiscal 2018, which ended on September 30, 2018, Siemens generated revenue of €83.0 billion and net income of €6.1 billion. At the end of September 2018, the company had around 379,000 employees worldwide. Further information is available on the Internet at www.siemens.com.

Click to comment

Power

Nigeria To Face Increase In Electricity Tariffs From July

Published

on

 

According to reports, Nigeria’s population may face more challenging times ahead as electricity tariffs are projected to increase by over 40 percent in the near future.

 

This rise in tariffs could ultimately result in the elimination of all energy subsidies in the country.

 

Currently, the electricity sector relies on a monthly subsidy of approximately N50 billion, stemming from a shortfall in revenue.

 

The tariff hike, scheduled to take effect from July 1, will pose another significant test for President Bola Ahmed Tinubu’s administration and its ongoing market reforms.

 

The government has already taken steps to remove subsidies on Premium Motor Spirit (PMS) and implemented a floating exchange rate for the national currency.

 

These decisions have added complexity to the price-setting process of the Nigerian Electricity Regulatory Commission (NERC) and its 2022 Multi-Year Tariff Order (MYTO).

 

Despite power sector players failing to meet the target of supplying a minimum of 5,000 megawatts, even after signing contracts with the Nigerian Electricity Regulatory Commission (NERC), the current Service Based Tariff (SBT) is based on an exchange rate of N441/$ and an inflation rate of 16.97 percent.

 

According to NERC’s directives in 2015, the average tariff for distribution companies (DisCos) and different categories of end-users was N25 per kilowatt, as per Order 198/2020, which came into effect on September 1, 2020.

 

However, in the MYTO for 2022, the average tariff increased to N60 per kilowatt across all customer categories, and in the most recent update, it stands at N64 per kilowatt.

 

The determination of the 2015 tariff relied on a foreign exchange rate of N198.97/$, which increased to N383.80/$ in 2020 and further to N441.78/$ in 2022. In terms of inflation, the 2015 MYTO utilized an 8.3 percent rate, which rose to 12 percent in 2020 and reached 16.97 percent in 2022.

 

Currently, the inflation rate stands at 22.41 percent, and experts predict it could reach 30 percent by the end of June, considering the floating of the naira and the removal of subsidies on Premium Motor Spirit (PMS).

 

The tariff determination process takes into account various factors, including the significant metering gap of over seven million, gas prices, losses within the system, and the actual generation capacity. These elements play a role in determining the final tariff.

 

As anticipated, NERC had projected that the tariff for July 2023 would eliminate subsidies and introduce increases to the previously frozen tariff bands D and E.

 

These adjustments were intended to raise the bands from N54.59/kilowatt to N62.16 for band D and from N48.37/kilowatt to N61.16 on average. Moreover, the average increase across all bands was expected to reach N67/kilowatt.

 

However, due to the ongoing floating of the naira and the significant inflationary pressures, it is now projected that the new average tariff will need to be approximately N88/kilowatt for the power sector to recover its costs.

 

According to energy lawyer Madaki Ameh, the continuous and frequent increases in power tariffs are akin to a form of blackmail against electricity consumers.

 

Amen said “Indexing the cost of electricity on the dollar is a huge mistake because most of the inputs for electricity supply are local. The DisCos are also holding Nigerians to ransom by failing to increase the supply base, thereby spreading the tariffs across a broader spectrum of consumers to reduce the unit cost of electricity.”

 

He insisted that as long as there remain many unmetered consumers and many others not connected to the grid at all, the few consumers on the grid would continue to be subjected to unjust tariffs, which are not reflective of the quality of service delivered.

 

Ameh hoped that the signing into law of the new Electricity Act would mark “the beginning of light at the end of the long tunnel of inefficient and epileptic power supply in Nigeria.”

 

Segun Ajibola, the former President of the Chartered Institute of Bankers of Nigeria (CIBN) and a professor of Economics at Babcock University, highlighted that there remains a gap between the cost of electricity and the value it provides in exchange.

 

“Nigerians are still struggling to keep pace with the cost of energy for business and household use. If the electricity tariff goes up as envisaged, the question remains if there will be value for the quantum of electricity so paid for.

 

“The truth remains that if electricity supply is constant, of the right quantity and quality, the envisaged upward review in the tariff will be gladly absorbed by the populace,” he said.

 

Lanre Elatuyi, an Electricity Market Analyst, expressed that the recently implemented tariff rate would have significant implications. He emphasized that the devaluation of the Nigerian currency poses a major challenge for companies with dollar-denominated loans to repay.

 

He said “They will need more naira today to buy a dollar. They need to manage their exposure to foreign exchange risk. Even operators of hydro plants pay their concession fees in dollars. So, wholesale electricity price will be adjusted upward and this will get to the end users’ tariffs too.”

Continue Reading

Power

Buhari’s Gov, State Governors Secretly Sold 5 Power Plants – Shehu Sani

Published

on

 

Senator Shehu Sani, a prominent Nigerian lawmaker has accused President Muhammadu Buhari’s government and state governors of secretly selling five power generating plants without disclosing the utilization of the funds received.

 

He disclosed this in his Twitter handle on Monday.

 

Senator Sani, known for his outspoken nature and activism expresses his concerns over the alleged undisclosed sale of the power plants.

 

He claimed that the government, in collaboration with state governors, had carried out the transactions without informing the Nigerian public about the purpose of the funds acquired from the sale.

 

The post reads “Buhari’s Government in collaboration with the State Governors quietly sold the five power generating plants without telling the country what the money was used for.

Continue Reading

Power

Nigeria’s VP Inaugurates 240MW Afam 3 Fast Power Project

Published

on

 

The Vice President of Nigeria, Prof. Yemi Osinbajo, has inaugurated the Afam 3 Fast Power 240-megawatt turbine project in Rivers State.

 

The project, which is a subsidiary of the Transcorp Group located in Oyigbo, on the outskirts of Port Harcourt in the state, was unveiled during a ceremony that took place on Tuesday.

 

The event, which was attended by several dignitaries, including the Chairman of Transcorp Group, Tony Elumelu, and other top officials, saw the Vice President arriving at the venue in a chopper at exactly 11:35 am.

 

Upon his arrival, he was escorted into the premises where he officially inaugurated the project.

 

During his speech at the event, he disclosed that the acquisition of the project was approved by the National Council on Privatisation (NCP) and the acquisition cost was ₦105.3 trillion.

 

Osinbajo further emphasized that the successful completion of the project is a significant breakthrough in Nigeria’s power sector.

 

In his address, Osinbajo said, “In 2020, electricity subsidies reached N584 billion, but service-based tariffs have led to a doubling of collection in the Nigeria Electricity Supply Industry from N40 billion in 2020 to N80 billion in the first quarter of 2023.

 

“If this trajectory continues, the Nigeria Electricity Supply Industry will be able to pay for itself. Our administration has also created programs for off-grid for electrification. Rural Electrification Agency now has the capacity to provide electricity supply on a first-class basis.

 

“We are on track to electrify all Nigerians in the next decade. However, we will not make progress if our gas supply does not improve. The gas supply challenges are hampering improvements.”

 

He further lauded General Electric, the National Council on Privatization (NCP), and the host communities for their contribution to the completion of the Afam 3 Fast Power 240-megawatt turbine project in Rivers State.

 

Osinbajo highlighted that the successful completion of the project will significantly increase the country’s power supply capacity, leading to a better quality of life for Nigerians.

 

In November 2020, the federal government and the Transcorp Power Consortium signed a share sale and purchase agreement in relation to Afam Power Plc and Afam 3 Fast Power Limited.

 

The National Council on Privatization approved the privatization of the Afam Power Plant back in August 2017, which triggered a competitive bidding process involving 12 prospective investors.

 

After careful consideration, Transcorp Power Consortium emerged as the preferred bidder with a combined offer of N105 billion.

Continue Reading

Copyright © 2022. Biztellers, powered by Alphaxristi.