ABUJA – The Bureau of Public Enterprises, BPE, says the physical handover of the Power Holding Company of Nigeria’s successor generation and distribution firms to their new owners may not hold on November 1, 2013 as earlier scheduled.

Director-General, BPE, Mr. Benjamin Dikki, said the agency would not affirm the date of the physical handover yet until it was certain that all labour issues had been adequately settled.

He spoke on the sidelines of a power expo organised by the Federal Ministry of Power in Abuja on Thursday.

Mr. Benjamin DikkiDikki also announced that almost the entire $3bn generated from the sale of the electricity generation and distribution companies would be used to settle the severance entitlements of the workers.

The BPE had announced last week that it made $3bn from the sale of the power assets.

On why the Federal Government was unsure of the handover date to the new owners of the power firms, the BPE boss said the agency was still reviewing the issues.

He added, “The official handover date will be announced appropriately. We are meeting tomorrow (today) to review the issues. If we think the issues that need to be addressed are properly addressed and that a handover can take place before or after November 1, we will announce to you.

“We want to make sure that the handover is done when all the critical issues like labour concerns are properly addressed. We will assess the progress of the payment exercise, find out if the bulk of the workers have received bank alerts for the severance package and the pension payout, and other issues.

“So, when we think all the critical issues have been properly addressed, then we will announce when we will do the formal handover.”

Asked to state how much of the $3bn would be used to settle the PHCN workers, Dikki said, “Virtually all of it is going to labour payment. This has been communicated to them that the proceeds from the sale are going to be used to address the labour issues.

“There are many ways of corroborating this information. You can go and verify. The BPE has remitted the money to the Accountant-General of the Federation’s office. The account-general’s office is in the process of remitting the money to their individual Retirement Savings Accounts. I don’t see what is hidden in this thing that should cause any ground for apprehension.”

Earlier, the Minister of Power, Prof. Chinedu Nebo, had said by the end of the first quarter of next year, all the 10 National Integrated Power Projects in the country would have been inaugurated.

He added that the government was working hard to ensure that it also put in place the facilities that would be capable of wheeling out the targeted 10,000 megawatts of electricity that would be generated before the first quarter of next year.

Nebo said, “Nigeria produces and consumes per capita only 2.5 per cent of what South Africa is producing and consuming. In order to be at par with South Africa, we need to increase our production and consumption of electricity.

“In other words, we shouldn’t be talking about 4,000MW or 10,000MW. By the end of 2014, we should be talking about 160,000MW. This is because the opportunities are there.”

The minister said not all Nigerians were connected to the national grid because the Federal Government did not have the resources to make sure that every community in the country was connected.

He added, “The investment needed will cripple the entire budget of the country. So, we are looking for partners to take power to the rural areas, and that is why we are working out modalities to make sure that Nigeria has a robust power base. Not just the gas-fired or hydro power turbines, but also coal generation, solar, wind and biomass.

“It is only when we begin to explore these energy sources that we will be able to get power to the remote areas that are not yet connected to the national grid.”

– THE PUNCH

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Power

Nigeria To Face Increase In Electricity Tariffs From July

Published

on

 

According to reports, Nigeria’s population may face more challenging times ahead as electricity tariffs are projected to increase by over 40 percent in the near future.

 

This rise in tariffs could ultimately result in the elimination of all energy subsidies in the country.

 

Currently, the electricity sector relies on a monthly subsidy of approximately N50 billion, stemming from a shortfall in revenue.

 

The tariff hike, scheduled to take effect from July 1, will pose another significant test for President Bola Ahmed Tinubu’s administration and its ongoing market reforms.

 

The government has already taken steps to remove subsidies on Premium Motor Spirit (PMS) and implemented a floating exchange rate for the national currency.

 

These decisions have added complexity to the price-setting process of the Nigerian Electricity Regulatory Commission (NERC) and its 2022 Multi-Year Tariff Order (MYTO).

 

Despite power sector players failing to meet the target of supplying a minimum of 5,000 megawatts, even after signing contracts with the Nigerian Electricity Regulatory Commission (NERC), the current Service Based Tariff (SBT) is based on an exchange rate of N441/$ and an inflation rate of 16.97 percent.

 

According to NERC’s directives in 2015, the average tariff for distribution companies (DisCos) and different categories of end-users was N25 per kilowatt, as per Order 198/2020, which came into effect on September 1, 2020.

 

However, in the MYTO for 2022, the average tariff increased to N60 per kilowatt across all customer categories, and in the most recent update, it stands at N64 per kilowatt.

 

The determination of the 2015 tariff relied on a foreign exchange rate of N198.97/$, which increased to N383.80/$ in 2020 and further to N441.78/$ in 2022. In terms of inflation, the 2015 MYTO utilized an 8.3 percent rate, which rose to 12 percent in 2020 and reached 16.97 percent in 2022.

 

Currently, the inflation rate stands at 22.41 percent, and experts predict it could reach 30 percent by the end of June, considering the floating of the naira and the removal of subsidies on Premium Motor Spirit (PMS).

 

The tariff determination process takes into account various factors, including the significant metering gap of over seven million, gas prices, losses within the system, and the actual generation capacity. These elements play a role in determining the final tariff.

 

As anticipated, NERC had projected that the tariff for July 2023 would eliminate subsidies and introduce increases to the previously frozen tariff bands D and E.

 

These adjustments were intended to raise the bands from N54.59/kilowatt to N62.16 for band D and from N48.37/kilowatt to N61.16 on average. Moreover, the average increase across all bands was expected to reach N67/kilowatt.

 

However, due to the ongoing floating of the naira and the significant inflationary pressures, it is now projected that the new average tariff will need to be approximately N88/kilowatt for the power sector to recover its costs.

 

According to energy lawyer Madaki Ameh, the continuous and frequent increases in power tariffs are akin to a form of blackmail against electricity consumers.

 

Amen said “Indexing the cost of electricity on the dollar is a huge mistake because most of the inputs for electricity supply are local. The DisCos are also holding Nigerians to ransom by failing to increase the supply base, thereby spreading the tariffs across a broader spectrum of consumers to reduce the unit cost of electricity.”

 

He insisted that as long as there remain many unmetered consumers and many others not connected to the grid at all, the few consumers on the grid would continue to be subjected to unjust tariffs, which are not reflective of the quality of service delivered.

 

Ameh hoped that the signing into law of the new Electricity Act would mark “the beginning of light at the end of the long tunnel of inefficient and epileptic power supply in Nigeria.”

 

Segun Ajibola, the former President of the Chartered Institute of Bankers of Nigeria (CIBN) and a professor of Economics at Babcock University, highlighted that there remains a gap between the cost of electricity and the value it provides in exchange.

 

“Nigerians are still struggling to keep pace with the cost of energy for business and household use. If the electricity tariff goes up as envisaged, the question remains if there will be value for the quantum of electricity so paid for.

 

“The truth remains that if electricity supply is constant, of the right quantity and quality, the envisaged upward review in the tariff will be gladly absorbed by the populace,” he said.

 

Lanre Elatuyi, an Electricity Market Analyst, expressed that the recently implemented tariff rate would have significant implications. He emphasized that the devaluation of the Nigerian currency poses a major challenge for companies with dollar-denominated loans to repay.

 

He said “They will need more naira today to buy a dollar. They need to manage their exposure to foreign exchange risk. Even operators of hydro plants pay their concession fees in dollars. So, wholesale electricity price will be adjusted upward and this will get to the end users’ tariffs too.”

Continue Reading

Power

Buhari’s Gov, State Governors Secretly Sold 5 Power Plants – Shehu Sani

Published

on

 

Senator Shehu Sani, a prominent Nigerian lawmaker has accused President Muhammadu Buhari’s government and state governors of secretly selling five power generating plants without disclosing the utilization of the funds received.

 

He disclosed this in his Twitter handle on Monday.

 

Senator Sani, known for his outspoken nature and activism expresses his concerns over the alleged undisclosed sale of the power plants.

 

He claimed that the government, in collaboration with state governors, had carried out the transactions without informing the Nigerian public about the purpose of the funds acquired from the sale.

 

The post reads “Buhari’s Government in collaboration with the State Governors quietly sold the five power generating plants without telling the country what the money was used for.

Continue Reading

Power

Nigeria’s VP Inaugurates 240MW Afam 3 Fast Power Project

Published

on

 

The Vice President of Nigeria, Prof. Yemi Osinbajo, has inaugurated the Afam 3 Fast Power 240-megawatt turbine project in Rivers State.

 

The project, which is a subsidiary of the Transcorp Group located in Oyigbo, on the outskirts of Port Harcourt in the state, was unveiled during a ceremony that took place on Tuesday.

 

The event, which was attended by several dignitaries, including the Chairman of Transcorp Group, Tony Elumelu, and other top officials, saw the Vice President arriving at the venue in a chopper at exactly 11:35 am.

 

Upon his arrival, he was escorted into the premises where he officially inaugurated the project.

 

During his speech at the event, he disclosed that the acquisition of the project was approved by the National Council on Privatisation (NCP) and the acquisition cost was ₦105.3 trillion.

 

Osinbajo further emphasized that the successful completion of the project is a significant breakthrough in Nigeria’s power sector.

 

In his address, Osinbajo said, “In 2020, electricity subsidies reached N584 billion, but service-based tariffs have led to a doubling of collection in the Nigeria Electricity Supply Industry from N40 billion in 2020 to N80 billion in the first quarter of 2023.

 

“If this trajectory continues, the Nigeria Electricity Supply Industry will be able to pay for itself. Our administration has also created programs for off-grid for electrification. Rural Electrification Agency now has the capacity to provide electricity supply on a first-class basis.

 

“We are on track to electrify all Nigerians in the next decade. However, we will not make progress if our gas supply does not improve. The gas supply challenges are hampering improvements.”

 

He further lauded General Electric, the National Council on Privatization (NCP), and the host communities for their contribution to the completion of the Afam 3 Fast Power 240-megawatt turbine project in Rivers State.

 

Osinbajo highlighted that the successful completion of the project will significantly increase the country’s power supply capacity, leading to a better quality of life for Nigerians.

 

In November 2020, the federal government and the Transcorp Power Consortium signed a share sale and purchase agreement in relation to Afam Power Plc and Afam 3 Fast Power Limited.

 

The National Council on Privatization approved the privatization of the Afam Power Plant back in August 2017, which triggered a competitive bidding process involving 12 prospective investors.

 

After careful consideration, Transcorp Power Consortium emerged as the preferred bidder with a combined offer of N105 billion.